Project Schedule
The following is the schedule planned for this project:
PHASE I SCHEDULE - Beam, decking, and roof work
20 March 2009 - Place advertisements
25 March 2009 - 10:00AM Pre-bid meeting
3 April 2009 - Last day for questions
10 April 2009 - Bids due at LHC
1 May 2009 - Work must start by this date
30 June 2009 - Work must be completed by this date.